- Reduced costs
9. Lean transformation at an automotive manufacturing site
Client Sector:
Manufacturing
Summary Results:
  • Manufacturing lead time fell from 13.5 days to 5.9 days
  • Manufacturing volumes increased by 73%
  • Plant inventory turns increased from 8 to 13 annually.
11. H&S: Replacement of open blades on the shop floor
Client Sector:
Manufacturing
Summary Results:
  • Certified team-based lean six sigma yellow belt project
  • H&S training in retractable knife use
  • Post implementation survey = high satisfaction rating
  • Reduced accident risk